Employer: İstanbul Water and Sewerage Administration
Project Location: İstanbul, Turkey
Date of Completion: 30.06.2012
Scope of Work:
• Wastewater treatment plant with a capacity of 400.000 m³/day,
• 6 sludge digesters with a capacity of 10.000 m³ each,
• Sludge drier unit with a capacity of 600 tons/day
• Cogeneration power plant with a capacity of 2 x 4,6 MW