Employer: State Hydraulics Works (DSI)
Consultant : NIPPON KOEI – GINN
Project Location : Istanbul, Turkey
Date of Completion: 14.12.2007
Scope of Work: Installation of spIral welded steel pipes wIth a diameter of Ø2.540 mm and special parts (18.964 MT) between Kincili Sirti and Agva, weldIng checks of the existing installed Ø2.540 mm diameter 16.486 MT steel pipe and repairing 9.429.65 MT, 122 art structures (line valve room, evacuation room, suction chamber and excavation-filling works).